City of Westminster
| Location | Project | Start Date | Est. Finish Date | Hours | Notes | Progress |
|---|---|---|---|---|---|---|
| Warwick Crescent | 28-04-08 | 27-06-08 | ||||
| Lords Hill | Ducting, Bridge and paving works | 05-05-08 | 20-06-08 | |||
| Praed St | Trial Holes | 09-06-08 | 20-06-08 | |||
| Mortimer St | 09-06-08 | 29-08-08 | ||||
| Connaught St | 09-06-08 | 13-06-08 | ||||
| St Martin In The Field | Civils | 9 June 2008 | 18 August 2008 | Site Manager: Paul Williams Site Supervisor: Pat Crane | ||
| 20 Gresham Street | Civils | 9 June 2008 | 25 August 2008 | Site Manager: Paul Williams |