LocationProjectStart DateEst. Finish DateHoursNotesProgress
33 HolbornFootway Works01/11/0714/04/08WeekdaysTerm Maintenance
Bow Lane (Phase 2)Carriageway & Footway07/04/0807/06/08WeekdayTerm MaintenanceDelay to works recommencement due to necessary diversion of Statutory Services by others
New StreetCarriageway & footway work01/10/0715/05/08WeekdaysTerm MaintenanceWorks delayed due to necessary Statutory Services diverted by others
New Street Square (Phase 2)Carriageway & footway work01/09/0715/07/08WeekdaysTerm MaintenanceWorks will stop in July for at least six months due to new development fit-out.
Grants Quay WharfCarriageway & footway work11/02/0831/07/08WeekdaydWorks delayed due to design issues
Lime StreetCarriageway & footway work07/01/0831/05/08WeekdaysTerm Maintenance
Primrose StreetCarriageway & footway work25/02/0830/10/08WeekdaysTerm MaintenanceWorks delayed for one month due to issues surrounding road closure.
Foster LaneCarriageway & footway work19/04/0831/07/08WeekdaysTerm Maintenance
Carter Lane (Phase 1)Carriageway & footway work31/07/08 (Estimated)30/07/09 (Estimated)WeekdaysTerm MaintenanceProvisional dates at present
Mansion House GyratoryCarriageway & footway work30/08/08 (Estimated)30/01/09 (Estimated)WeekdaysTerm MaintenanceProvisional dates at present