| Location | Project | Start Date | Est. Finish Date | Hours | Notes | Progress |
|---|---|---|---|---|---|---|
| Lennard Road Penge Part | 25/05/08 | 13/06/08 | Weekdays | Term Maintenance | ||
| Aviemore Way Beckenham | 23/03/08 | 07/06/08 | Weekdays | Term Maintenance | ||
| Pickhurst Lane (Summer Holidays) | 08/06/08 | 05/09/08 | Weekdays | Term Maintenance | ||
| Addington Road | 20/04/08 | 07/06/08 | Weekdays | Term Maintenance | ||
| Church House Gardens | 11/05/08 | 05/07/08 | Weekdays | Term Maintenance | ||
| Town Court Crescent (Summer Holidays) | 27/07/08 | 05/09/08 | Weekdays | Term Maintenance | ||
| Sandybury (Part Summer Holidays) | 17/08/08 | 05/09/08 | Weekdays | Term Maintenance |